CITY of RAPID CITY

Agenda Item Summary

 

Public Works Committee Meeting Date: 7/28/2015

City Council Meeting Date: 8/3/2015

Staff Contact: Klare Schroeder

Petitioner: Click here to enter text.

Location:

 

Agenda Title:

Approve Change Order No. 10 to Scull Construction Service Inc. for Canyon Lake Dam Reconstruction, Project No. 08-1743 / CIP No. 50739, for an increase of $15,460.52.

 

Summary:

Increase to contract based on actual quantities of riprap installed.

Funding Source & Fiscal Impact (if applicable):

 

Fund

Cost Center

 

Fund

Cost Center

Vision

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

x

Budgeted

 

 

Not Budgeted

Recommendation:

Action: Approve

Notes:

City Council Options:

 

Attachments & Links:

Change Order

 

 

 

 

 

Click here to enter text.

Click here to enter text.

Click here to enter text.